Plan an Easee installation
Choose compatible chargers, complete the electrical design, configure the site and hand it over.
Use this guide to move from product and circuit planning to site configuration and customer handover. It provides orientation only: the exact product guide, a site-specific electrical design and applicable regulations remain authoritative.
01Confirm responsibility and access
Before choosing equipment, confirm who is responsible for the electrical design and that the installer can configure the Easee site.
Authorised electrician required
Easee products may only be installed, repaired or serviced by an authorised electrician. Follow the exact product guide and all applicable local, regional and national regulations.
Confirm Installer Company access
The Easee account used for configuration must be connected to an Installer Company. If the company already exists, ask its administrator to add the installer instead of creating a duplicate.
Create or join an Installer CompanyPrepare the Installer App
Use a phone that supports NFC or Bluetooth. NFC can program a backplate before the Chargeberry is fitted; supported Bluetooth flows require the Chargeberry to be installed and powered.
Set up the Installer App02Choose the product group and circuit
Once installer access is ready, use the charger model—not the site type in the app—to decide which products may share a circuit.
| Product group | Current models | Chargers per circuit | Electrical limit |
|---|---|---|---|
| SDU | Charge Up, Charge Max and market-specific Easee One | Up to 3 | Circuit protection up to 40 A; maximum short-circuit current 10 kA. |
| MDU | Charge Core and Charge Pro | Up to 101 | Circuit protection up to 80 A; maximum short-circuit current 10 kA. |
Keep one product group per circuit
SDU and MDU chargers cannot form one load-balancing group. A site may contain several circuits when the site-specific design supports it. Confirm product availability, approvals and exact limits for the selected market and variant.
Check charger compatibility and communication03Complete the electrical design
After the product group and circuit boundary are known, size the installation for present demand, site conditions and planned expansion.
Define present and future demand
Confirm the number of charging points, expected use and whether more chargers or Easee Ready backplates may be added later.
Assess the supply and grid
Verify the incoming supply, grid system, available phases and any site-specific limitations on three-phase charging.
Choose conductors and protection
Determine the cable route, conductor size, overcurrent protection, overvoltage protection and any upstream residual-current protection required for the supply cable.
Plan load balancing
Chargers in one circuit distribute the available current dynamically. Add an Easee Equalizer when charging must also adapt to the building's available capacity, and keep the phase sequence consistent at the meter and chargers.
Show Easee planning recommendations
- Consider a three-phase installation when the grid, vehicle and local requirements support it.
- Use the largest conductor cross-section approved for the exact product and installation method when future expansion is expected.
- Consider Easee Ready backplates and blind covers where future charging points are planned.
| 63 A · TN 400 V · three-phase | Up to 25 chargers |
|---|---|
| 63 A · IT 230 V · three-phase | Up to 15 chargers |
These are planning recommendations, not product limits or a substitute for the site-specific electrical design.
Review Easee Ready for planned expansion04Install from the exact product guide
With the electrical design complete, use the installer guide for the selected product and variant for every physical installation value and action.
The product guide is the installation procedure
Do not use this overview to set clearances, conductor preparation or terminal torque. Confirm those values in the current guide before starting work.
Position
Confirm accessibility, installation height, required clearances, wall suitability and impact protection.
Connect
Follow the wiring, conductor preparation, phase identification and tightening instructions in the exact product guide.
Fit
Seat the Chargeberry fully in the backplate. If it does not click securely into place, inspect the pins and connectors before continuing.
Secure
Use the documented theft-protection method before fitting the front cover.
Installation overview video
The video is supplementary and does not replace the installer guide for the exact product.
05Configure and upload the site
After the hardware is installed according to its guide, transfer the verified site and circuit design into the Installer App.
Create the site
Select the correct site type and enter the required site information and address.
Enter the electrical values
Add the verified main fuse and charging-circuit fuse values from the site design.
Configure the chargers
Use the supported NFC or Bluetooth flow. With NFC, program every backplate with the correct site and circuit data before fitting the Chargeberry.
Upload to Easee Cloud
Check the circuit structure and charger configuration, then upload the completed site.
Follow the site-creation guideShow the information to prepare
- Site type, site name and address
- Operator details, when relevant
- Main fuse and charging-circuit fuse
- WiFi network details
- Future Site Owner or Administrator
06Complete the handover
Once the site is uploaded, give the customer the installation records and transfer ownership to the intended Site Owner.
Store the charger details
Record the serial number and PIN from the Chargeberry sticker and leave the information in an agreed secure location for the owner.
Send the ownership transfer
Use the Installer App or Easee Control to invite the intended Site Owner by email or a generated sharing link.
Review the ownership-transfer processConfirm acceptance
The customer signs in or creates an Easee account and accepts the transfer. Ownership changes only after the invitation is accepted.
Explain site management
Show the customer the agreed charging and management method. Larger or shared sites may be managed in Easee Control or by a charging operator.
The installation is ready for the owner
The product is configured and online, the transfer has been accepted, and the owner has the records and management route agreed for the site.
If site configuration or ownership transfer still cannot be completed
Contact Easee Support
Include the charger serial number or site key, the product model, the step that failed and the exact message shown in the Installer App or Easee Control.